Addition of a new 32.4m diameter clarifier and all associated pipeworks etc. The clarifier was to be founded on precast driven piles, which design criteria included refusal against upward movement (floating) due to the high water table in the area. Large dia. HDPE pipes laid in deep water logged trenches under difficult circumstances.